BRM E-Scrap
Description
The site is located in a Flood Zone 3 area, which is an area identified by the Environment Agency as being at high risk of flooding. The site is bounded to the east by the tidal River Thames. The river frontage is characterised by hard engineered flood defences and intertidal mud flats.
The demolition required on this site was for the removal of a single storey 1960’s building and materials discarded by previous tenants. Demolition of the existing buildings, remove shallow foundations and ground beams, removed isolated utilities, removing top soil, break out hard standings and general site clearing and grubbing with no changes to the existing ground levels.
On completion of all the works we were required to survey the site levels at centres of no more than 5m, to the nearest 0.01 AOD.
Details
- Contract: BRM E-Scrap
- Client: Britannia Refined Metals
- Location: Nortfleet, Kent
- Value: £200,000
- Duration: 12 weeks
- Scope: Light Industrial